考虑脱网风险的新能源集群接入与区域电网协调扩展规划模型
CSTR:
作者:
作者单位:

(1.国网四川省电力公司经济技术研究院 ,四川 成都 610041;2.湖南大学电气与信息工程学院 ,湖南 长沙 410082)

作者简介:

通讯作者:

胡涛(2000—),男,硕士研究生,主要从事电力系统规划等方面的研究;E-mail:htao@hnu.edu.cn

中图分类号:

TM715

基金项目:

国网四川省电力公司科技项目(521996230006)


Coordinated expansion planning m odel of new energy cluster integration and regional power grid s considering off -grid risks
Author:
Affiliation:

(1.Electric Power Research Institute , State Grid Sichuan Electric Power Co ., Ltd., Chengd u 610041, China; 2.College of Electrical and Information Engineering , Hunan Univer sity, Changsha 410082, China)

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    在大型新能源集群与基地建设背景下,新能源汇集站并网线路故障可能造成较大的功率扰动,存在诱发新能源连锁脱网、恶化系统频率稳定性的风险。针对该问题,构建一种考虑脱网风险的新能源集群接入与区域电网协调扩展规划模型。先分析新能源集群接入下区域网架扩展规划存在的主要问题;再构建新能源集群接入与区域电网网架扩展的协调规划模型;然后,在新能源站群优化中,考虑汇集站并网线路利用率的约束,在区域网架规划模型中,考虑汇集站并网线路故障情况下大规模新能源脱网风险相关约束 (系统频率变化率、频率偏差和故障后线路潮流约束 );最后,基于改进的 IEEE RTS- 79系统开展算例分析,验证所提模型和规划方案的有效性。

    Abstract:

    Against the backdrop of large-scale new en ergy clusters and base construction,faults in the grid-connection lines of new energy collection stations may cause significant power disturbances,posing risks of inducing the cascading off-grid occurrence of new energy sources and deteriorating system frequency stability.To this end,this paper builds a coordinated expansion planning model for new energy cluster integration and regional power grids,with off-grid risks considered.Firstly,the main problems in the regional grid expansion planning under the integration of new energy clusters are analyzed.Subsequently,a coordinated planning model of new energy cluster integration and the expansion of regional power grid structures is built.Then,in the optimization of new energy station clusters,by considering the constraints of the utilization rate of grid-connected lines at the collection stations,the regional grid planning model takes constraints related to large-scale new energy off-grid risks under faults of grid-connected lines at collection stations into account,including the system frequency rate of change,frequency deviation,and post-fault line flow constraints.Finally,a case analysis based on the improved IEEE RTS- 79 system is conducted to validate the effectiveness of the proposed model and planning scheme.

    参考文献
    相似文献
    引证文献
引用本文

苏韵掣,刘阳,王潇笛,等.考虑脱网风险的新能源集群接入与区域电网协调扩展规划模型[J].电力科学与技术学报,2025,(4):12-23.
SU Yunche, LIU Yang, WANG Xi aodi, et al. Coordinated expansion planning m odel of new energy cluster integration and regional power grid s considering off -grid risks[J]. Journal of Electric Power Science and Technology,2025,(4):12-23.

复制
分享
相关视频

文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:2024-04-20
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2025-10-27
  • 出版日期:
文章二维码